Red Line (Mumbai Metro)

Red Line
Overview
StatusOperational: 7-Red Line
Partially operational: 9-Red Line
Under construction: 7A-Red Line
Owner MMRDA
Line number7, 7A, 9
Locale
Termini
Connecting lines
Stations21 (operational) / 23 (total)
Websitehttps://www.mmmocl.co.in/
Service
TypeRapid transit
SystemMumbai Metro
OperatorMaha Mumbai Metro Operation Corp. Ltd. (MMMOCL)
DepotCharkop
Rolling stockBEML
History
Opened2 April 2022 (2022-04-02)
Technical
Line length31.045 km (19.290 mi)
Number of tracks2
CharacterElevated and underground
Track gauge1,435 mm (4 ft 8+1⁄2 in) standard gauge
Electrification25 kV 50 Hz AC (overhead line)
Route map

Red Line
km
Dongri Depot
8.3346
Subhash Chandra Bose Stadium
7.6960
Shahid Bhagat Singh Garden
Western line
6.2642
Deepak Hospital (Medtiya Nagar)
5.0171
Sai Baba Nagar
3.7171
Kashigaon
2.7971
Miragaon
1.9963
Pandurang Wadi
to Yellow Line
0.0000
Dahisar East
1.1404
Ovaripada
2.1484
Rashtriya Udyan
3.2749
Devipada
4.0972
Magathane
5.8249
Poisar
6.4492
Akurli
7.4569
Kurar
8.3449
Dindoshi
9.4249
Aarey
11.7434
Goregaon East
13.1111
Jogeshwari East
JVLR Junction on Pink Line
14.2951
Mogra
15.5249
Gundavali
Western Express Highway on Blue Line
16.0849
Airport Colony
to Aqua Line
18.9342
Chhatrapati Shivaji Maharaj
International Airport - T2
Chhatrapati Shivaji Maharaj International Airport
to Gold Line

The Red Line is part of the Mumbai Metro rail network for the city of Mumbai, Maharashtra, India. During construction, the line was divided into three smaller lines – Line 7 (Dahisar (East) to Gundavali), Line 7A (Gundavali to Chhatrapati Shivaji Maharaj International Airport - T2), and Line 9 (Subhash Chandra Bose Stadium to Dahisar (East)).

The 31.045 km corridor connects the region of Mira-Bhayandar to the Chhatrapati Shivaji Maharaj International Airport via Andheri (East) and Dahisar (East). Construction of Line 7 began in August 2016, while construction of Lines 7A and 9 began in March 2020. The majority of the corridor is elevated, with only the airport section being underground.

There are a total of 23 stations planned on the corridor, of which 21 are elevated and 1 is underground. The line offers interchange with:

The line is also proposed to have interchanges with the Green Line and the Gold Line.

On 7 April 2026, the Red Line was extended northward into Mira-Bhayandar with the opening of Phase 1 of Line 9, covering three stations from Dahisar (East) to Kashigaon. Commercial services began on 8 April 2026.

Stations opened in this phase are:

  1. Dahisar East metro station (Interchange with Metro Line 2A)
  2. Pandurang Wadi metro station
  3. Miragaon metro station (Interchange with approved Metro Line 10)
  4. Kashigaon metro station