Line 1 (Ho Chi Minh City Metro)

Line 1
L1
A Line 1 train approaching Van Thanh Park station
Overview
Native nameTuyến 1
StatusOperational
OwnerVietnam Railways - Management Authority for Urban Railways (MAUR)
LocaleHo Chi Minh City, Vietnam
Termini
Stations14
WebsiteHCMC Metro Line 1 Guideline
Service
TypeRapid transit
System Ho Chi Minh City Metro
OperatorHURC1
DepotLong Binh
Rolling stockHitachi, 3 cars per train set
Daily ridership56,326 (daily)
~110,000 (peak during Tet holiday)
Ridership20,558,990 (2025)
History
Opened22 December 2024
(1 year, 8 months and 3 weeks)
Technical
Line length19.7 kilometers (12.2 mi)
Number of tracks2
Track gauge1,435 mm (4 ft 8+1⁄2 in) standard gauge
Electrification1,500 V DC from overhead catenary
Operating speed110 km/h (68 mph) elevated
80 km/h (50 mph) underground
35 km/h (22 mph) to station
25 km/h (16 mph) in station
Route map

Up arrow An Ha
UpperLeft arrow Tan Kien
L3
Cong Hoa Roundabout
Hiep Binh LowerRight arrow
L3
Thai Binh Market
Left arrow Hiep Phuoc
L4
Cu Chi UpperRight arrow
Left arrow Can Gio
L1-01
Ben Thanh
LowerLeft arrow Thu Thiem
Đong Thanh Right arrow
L4
L1-02
Opera House
L1-03
Ba Son
Nhieu Loc – Thi Nghe Canal
Van Thanh Canal
Nguyen Huu Canh Street
L1-04
Van Thanh Park
New Can Giuoc Bus Terminal UpperRight arrow
L5
Đien Bien Phu Boulevard
L1-05
Tan Cang
L1-06
Thao Dien
Left arrow Tan Kien – Thanh Da Right arrow
L7
L1-07
An Phu
LowerLeft arrow Song Tac Bus Terminal
L5
L1-08
Rach Chiec
Rach Chiec
Left arrow Long Binh – Thanh Da Right arrow
L7
L1-09
Phuoc Long
Binh Trieu Right arrow
L6
L1-10
Binh Thai
Left arrow Phu Huu
L6
Ring Road 2
L1-11
Thu Duc
Vo Van Ngan Street
Cai Stream
Left arrow Thu Thiem – Tham Luong Right arrow
L10
L1-12
High Tech Park
L1-13
National University
L1-14
Suoi Tien Terminal
LowerRight arrow Binh Duong
Down arrow Long Thanh International Airport
Long Binh Depot

Line 1 of the Ho Chi Minh City Metro (Vietnamese: Tuyến số 1 của hệ thống đường sắt đô thị Thành phố Hồ Chí Minh) is a rapid transit line in Ho Chi Minh City, Vietnam. It is the city's first metro line and the nation's first underground metro line, connecting the city center with the east side, including former District Bình Thạnh and Thủ Đức City.

Construction began in 2012, with an initial completion date set for 2018. However, the project's completion was delayed multiple times. The line was officially opened for service on 22 December 2024.

Ticket prices range from 7,000–20,000 VND (US$0.27–0.79) per trip or 6,000–19,000 VND (US$0.20–0.75) for cashless payments.

From the planning in 2024, Line 1 will be extended from Ben Thanh station to An Ha Depot, bringing the total length to 40.8 km.