John Horgan Dam

John Horgan Dam
Dam construction as of May 2025
John Horgan Dam is located in British Columbia
John Horgan Dam
John Horgan Dam
Location within British Columbia
Official nameJohn Horgan Dam and Generating Station
LocationPeace River Regional District, British Columbia, Canada
Coordinates56°11′41″N 120°54′51″W / 56.19472°N 120.91417°W / 56.19472; -120.91417
StatusOperational
Construction began2015
Opening date2025
Construction costC$16 billion, February 2021 estimate
OwnerBC Hydro
Dam and spillways
Type of damEarth fill
ImpoundsPeace River
Height60 m (200 ft)
Length1,050 m (3,440 ft)
Reservoir
CreatesNáaché mege reservoir
Surface area9,330 ha (23,100 acres)
Power Station
Installed capacity1,100 MW
Annual generation5,100 GWh

The John Horgan Dam and Generating Station (formerly known as the Site C Dam) is a hydroelectric dam on the Peace River, 14 kilometres southwest of Fort St. John in northeastern British Columbia, Canada. It is located approximately 80 kilometres downstream from the W. A. C. Bennett Dam.

It is the fourth largest producer of hydroelectricity in British Columbia. Its six generating units have an installed capacity of 1,100-1,230 MW and an annual output of approxmiately 5,100 GWh of electricity.

The dam created the Site C reservoir, named Nááchę mege (pronounced nah chay meegeh), which translates to Dreamer Lake. There are two public boat launches on Nááchę mege, at Lynx Creek and Halfway River, as well as a floating dock installed at the D.A. Thomas Recreation Area. A publicly accessible viewpoint is located immediately west of the Fort St. John, on the south side of Highway 97.

The project was controversial, and drew substantial opposition from several quarters due to its planned flooding of agricultural land, damage to the local environment, high construction cost, possible alternatives, and the uncertainty of future electricity prices and demand in the province. Two Treaty 8 First Nations and local landowners made legal challenges to the dam, though these were dismissed by the Federal Court of Appeal. In addition, over 200 scholars, as well as the Royal Society of Canada, expressed concerns to the federal Liberal government, citing weakness in the regulatory review process and the environmental assessment for the project. In May 2016, the federal government of Canada stated it is "not revisiting projects that have been reviewed and approved". On 11 December 2017, John Horgan, the premier of British Columbia, announced: "We've come to a conclusion that, although Site C is not the project we would have favoured or would have started, it must be completed", thus guaranteeing the completion of the project.

On 8 November 2024, BC Hydro announced that the reservoir was full and that the first generator was operational. The John Horgan Dam and Generating Station became fully operational on August 8, 2025.