Prototype Fast Breeder Reactor
| Prototype Fast Breeder Reactor | |
|---|---|
| Generation | Generation IV reactor |
| Reactor concept | Sodium-cooled fast reactor |
| Reactor line | IFBR (Indian fast-breeder Reactor) |
| Designed by | IGCAR |
| Manufactured by | BHAVINI |
| Status | Critical |
| Main parameters of the reactor core | |
| Fuel (fissile material) | Plutonium/235U |
| Fuel state | Solid |
| Neutron energy spectrum | Fast |
| Primary control method | Control rods |
| Primary coolant | Liquid sodium |
| Reactor usage | |
| Primary use | Breeding of 233U for AHWR-300 and generation of electricity |
| Power (thermal) | 1253 |
| Power (electric) | 500 |
| Prototype Fast Breeder Reactor | |
|---|---|
| Official name | आदिप्ररूप द्रुत प्रजनक रिएक्टर |
| Country | India |
| Location | Kokkilamedu, near Kalpakkam, Tamil Nadu, India |
| Coordinates | 12°33′11″N 80°10′24″E / 12.55306°N 80.17333°E |
| Status | Critical |
| Construction began | 2004 |
| Commission date | 2026 (planned) |
| Construction cost | ₹5,850 crore (equivalent to ₹220 billion or US$2.23 billion in 2023) |
| Owner | BHAVINI |
| Operator | BHAVINI |
| Nuclear power station | |
| Reactor type | Fast breeder |
| Thermal power station | |
| Primary fuel | |
| Cooling source | |
| Power generation | |
| Nameplate capacity | 500 MW |
The Prototype Fast Breeder Reactor (PFBR) is a 500 MWe pool type sodium-cooled, fast breeder reactor commissioned at the same site as the Madras Atomic Power Station in Kokkilamedu, near Kalpakkam, Tamil Nadu, India.
The indigenously developed reactor achieves a crucial second stage outlined in India's three stage nuclear power program building on the decades of experience gained from operating the lower power Kalpakkam Mini reactor (KAMINI) and Fast Breeder Test Reactor (FBTR). Since the PFBR, with closed fuel cycle as the energy resource, is capable of generating a large amount of uranium-233, a fissile isotope from thorium-232, it is instrumental in paving the way for utilization of India's abundant thorium reserves and reducing dependence on uranium import for its nuclear energy program, which has been a historical constraint in India's nuclear energy ambitions.
The project is commissioned by Bharatiya Nabhikiya Vidyut Nigam Limited (BHAVINI), a Public Sector Undertaking (PSU) under the Department of Atomic Energy (DAE), Indira Gandhi Centre for Atomic Research (IGCAR) is responsible for the design of this reactor, the Advanced Fuel Fabrication Facility at the affiliated campus of Bhabha Atomic Research Centre (BARC) in Tarapur is responsible for MOX fuel fabrication and Bharat Heavy Electricals Limited (BHEL) is providing technology and equipment for construction of the reactor.
Construction work on the reactor beginning in 2004, was supposed to be completed in September 2010 but upon facing several delays was completed on 4th March 2024. The project's cost has also more than doubled from ₹3,500 crore to ₹8,181 crore due to the multiple delays. The Prototype Fast Breeder Reactor successfully achieved first criticality on 6th April 2026 at 08:25 PM IST.