Manukau Branch

Manukau Branch
The trenched approach to Manukau station, the terminus, seen from the west.
Overview
StatusOpen
OwnerKiwiRail (track and platforms)
Auckland Transport (buildings)
Termini
Stations1
Service
TypeUrban rail
ServicesEast West Line
OperatorAuckland One Rail
Rolling stockAM class EMU
Daily ridership1,650 (April 2018)
History
Opened15 April 2012
Technical
Line length2.5 kilometres (1.6 mi)
Track length2.5
Number of tracksTwo
CharacterUrban
Track gauge1,067 mm (3 ft 6 in)
Electrification25 kV AC 2014
Route map

North Island Main Trunk
← Wellington │ Waitematā →
Puhinui
Plunket Ave
Lambie Drive
Manukau
Enabling works for the future rail line as part of the SH20 project in 2008. Looking west over Lambie Drive from just northwest of the future terminus station.

The Manukau Branch is a 2.5 kilometres (1.6 mi) spur railway line off the North Island Main Trunk railway from Wiri to Manukau City Centre in Auckland, New Zealand. It is the first fully new section of railway line constructed in Auckland since the Westfield Deviation in 1930. From Manukau, the branch connects to the NIMT in the north facing direction only.

The estimated cost of the project was $50 million. Construction began in June 2009 and the line opened on 15 April 2012.