Mackintosh Dam
| Mackintosh Dam | |
|---|---|
Mackintosh Dam Location of the dam in Tasmania | |
Interactive map of Mackintosh Dam | |
| Country | Australia |
| Location | Western Tasmania |
| Coordinates | 41°41′57″S 145°38′52″E / 41.699112°S 145.647769°E |
| Purpose | Power |
| Status | Operational |
| Opening date | 1981 |
| Owner | Hydro Tasmania |
| Dam and spillways | |
| Type of dam | Rock-fill dam |
| Impounds | Mackintosh River |
| Height | 75 m (246 ft) |
| Length | 465 m (1,526 ft) |
| Dam volume | 927×103 m3 (32.7×106 cu ft) |
| Spillways | 1 |
| Spillway type | Uncontrolled |
| Spillway capacity | 1,021 m3/s (36,100 cu ft/s) |
| Reservoir | |
| Creates | Lake Mackintosh |
| Total capacity | 913.69 GL (740,740 acre⋅ft) |
| Catchment area | 512 km2 (198 sq mi) |
| Surface area | 276.1 ha (682 acres) |
| Maximum length | 17.5 km (10.9 mi) |
| Maximum width | 3.5 km (2.2 mi) |
| Maximum water depth | 60 m (200 ft) |
| Normal elevation | 210 to 230 m (690 to 750 ft) AHD |
| Mackintosh Power Station | |
| Coordinates | 41°41′24″S 145°38′24″E / 41.69000°S 145.64000°E |
| Operator | Hydro Tasmania |
| Commission date | 1982 |
| Type | Conventional |
| Hydraulic head | 61 m (200 ft) |
| Turbines | 1 x 81 MW (109,000 hp) Fuji Francis-type |
| Installed capacity | 81 MW (109,000 hp) |
| Capacity factor | 0.85 |
| Annual generation | 394 GWh (1,420 TJ) |
| Website hydro.com.au | |
The Mackintosh Dam is a concrete-faced rock-fill embankment dam across the Mackintosh River, located in Western Tasmania, Australia. Located not far from the main dam is the Tullabardine Dam, a saddle dam across the Tullabardine Creek. Both dams were completed in 1981 and together they formed the resultant reservoir, Lake Mackintosh, established for the purpose of generating hydroelectricity via the Mackintosh Power Station, a conventional hydroelectric power station.
The dam, its reservoir, and the power station are owned and operated by Hydro Tasmania.