The wind turbine in February 2026, with the Seabank Power Station in the background
Official nameAmbition Community Energy CIC Wind Turbine
CountryEngland
LocationAvonmouth, Bristol
Coordinates51°32′16.5″N 2°40′26.4″W / 51.537917°N 2.674000°W / 51.537917; -2.674000
StatusOperational
Construction began4 July 2022
Commission dateMay 2023
Construction cost£5.5m
OwnersAmbition Community Energy CIC (ACE)
Thrive Renewables
OperatorAmbition Community Energy CIC
Wind farm
TypeOnshore
Hub height150 m (490 ft)
Rotor diameter115.7 m (380 ft)
Rated wind speed13.2 m/s (43 ft/s)
Power generation
Nameplate capacity4.25 MW
Annual net output10.9 GWh
External links
CommonsRelated media on Commons

The Lawrence Weston Wind Turbine, also known as the Ambition Community Energy Wind Turbine, is a community-owned wind turbine located in Avonmouth, Bristol, England, near the Seabank Power Station. It is situated beside the A403 road and Severn Estuary, just north of the Avonmouth Docks and Chittening industrial estate and south of Severn Beach, close to the boundary with South Gloucestershire. The wind turbine, which began operating in May 2023, serves to support the nearby Lawrence Weston subdivision by generating and selling electricity to the National Grid, where surplus revenue is then used to fund projects and infrastructure in the community. It's 150 metres (490 ft) in height, making it the tallest onshore wind turbine in England as well as the tallest structure in Bristol.

Ambition Lawrence Weston (ALW), a community-led charity group dedicated to supporting the community of Lawrence Weston, formed the offshoot community interest company Ambition Community Energy (ACE) to facilitate the creation of the wind turbine. Planning for the Lawrence Weston Wind Turbine began in late 2016 with negotiations between ACE and the Bristol City Council. By 2020, the wind turbine project was approved by the council and the government, with funding for the project acquired the following year through loans and grants from organisations such as Thrive Renewables and the West of England Combined Authority (WECA). Construction of the Lawrence Weston Wind Turbine began in mid-2022 and was completed in early May the following year.