Kudankulam Nuclear Power Plant
| Kudankulam Nuclear Power Plant | |
|---|---|
| Country | India |
| Coordinates | 8°10′08″N 77°42′45″E / 8.16889°N 77.71250°E |
| Status | Operational |
| Construction began | Unit 1: 31 March 2002 Unit 2: 4 July 2002 Units 3 & 4: 29 June 2017 Unit 5: 29 June 2021 Unit 6: 20 December 2021 |
| Commission date | Unit 1: 22 October 2013 Unit 2: 15 October 2016 |
| Construction cost | Units 1 & 2: ₹22,462 crore (US$4.76 billion) in 2001 prices Units 3 & 4 (Revised Cost): ₹68,893 crore |
| Owner | Nuclear Power Corporation of India |
| Operator | |
| Nuclear power station | |
| Reactors | 6 |
| Reactor type | PWR |
| Reactor supplier | Rosatom |
| Cooling source | Laccadive Sea |
| Thermal capacity | 2 × 3000 MWth |
| Power generation | |
| Units operational | 2 × 1000 MW (gross) |
| Make and model | VVER-1000/412 |
| Units under const. | 4 × 1000 MW (gross) |
| Nameplate capacity | 2000 MW |
| Capacity factor | 68.27% (2020–21) |
| Annual net output |
|
| External links | |
| Website | Nuclear Power Corporation of India |
| Commons | Related media on Commons |
Kudankulam Nuclear Power Plant (or Kudankulam NPP or KKNPP) is the largest nuclear power station in India, situated in Kudankulam in the Tirunelveli district of the southern Indian state of Tamil Nadu. Construction on the plant began on 31 March 2002, but faced several delays due to opposition from local fishermen. KKNPP is scheduled to have six VVER-1000 reactors built in collaboration with Atomstroyexport, the Russian state company and Nuclear Power Corporation of India Limited (NPCIL), with an installed capacity of 6,000 MW of electricity.
Unit 1 was synchronized with the southern power grid on 22 October 2013 and since then, has been generating electricity at its warranted limit of 1,000 MW.
In December 2025, Rosatom delivered the first batches of fuel to the plant, to be loaded into the core of the third power unit of the site. The TVS-2M fuel has been designed for a 18 month fuel cycle. Pre commissioning activities also began at the site of unit 3 in late 2025.