Terranora interconnector

Directlink (Terranora) Interconnector
Location of Directlink (Terranora) Interconnector
Location
CountryAustralia
StateNew South Wales
General directionsouth-north
FromMullumbimby
ToBungalora
Ownership information
OwnerEnergy Infrastructure Investments (EII)
OperatorAPA Group
Construction information
Cable manufacturer
ABB
Substation manufacturer
ABB
ContractorsTransÉnergie Australia
Commissioned2000
Technical information
TypeLand cable (buried)
Current typeHVDC VSC
Total length63 km (39 mi)
Capacity180 MW
AC voltage110 kV (Bungalora), 132 kV (Mullumbimby)
DC voltage±80 kV
No. of circuits3

Directlink (Terranora) Interconnector is a mixed buried and above ground 59 kilometre (37 mi) High Voltage Direct Current (HVDC) electricity transmission cable route from near Lavertys Gap (28°34′15″S 153°27′8″E / 28.57083°S 153.45222°E / -28.57083; 153.45222 (Directlink - Mullumbimby Static Inverter Plant)), 5 kilometres (3.1 mi) Southwest of Mullumbimby, New South Wales and Bungalora (28°15′20″S 153°28′20″E / 28.25556°S 153.47222°E / -28.25556; 153.47222 (Directlink - Bungalora Static Inverter Plant)) & connected via a 3.5 km (2.2 mi) AC Overhead Transmission Line to the NorthEast to the Terranora Electrical Substation (28°14′28.3″S 153°30′12.7″E / 28.241194°S 153.503528°E / -28.241194; 153.503528 (Essential Energy - Terranora Electrical Substation)) @ Terranora, New South Wales in Eastern Australia. The DC cables alternate between above ground in a galvanised steel trough and below ground with depths up to 1 metre.

It is one of the two interconnections used to trade electricity between New South Wales and Queensland (the other is the 330 kV Dual Circuit Queensland – New South Wales Interconnector (QNI)).